787 Bailey Hill Road
PO Box 21410
Eugene, Oregon 97402
541.484.1151 |
|
|
 |
Underground Services
Lane Electric Cooperative will need to inspect all ditches and
conduit prior to backfilling. Lane Electric will provide
and install a service conductor. Please remember to call
Utility Notification Center 1-800-332-2344
48 hours prior to digging.
|
| Underground Services |
Temporary Underground Installation

Notes:
- Consumer will supply conductors long enough to be connected
inside LEC’s transformer or secondary box. A
maximum of 3 feet from pole to transformer or secondary
box.
- Consumer
will supply all trench, meterbase, grounds, pole, and disconnect
switch.
- LEC will connect the consumer’s wire to the transformer
or secondary box and install the meter.
- Energizing of consumer’s service is contingent upon
an approved State or City electrical inspection.
Underground Service With An Underground Feeder

Notes:
- All electrical connections, equipment and equipment grounds
shall comply with the National Electrical Safety Codes.
- The
Consumer shall furnish and maintain a 6”x6”x10’ pressure
treated wood post, all conduit, conduit straps, grounds,
meterbase, disconnects, and electrical cable beyond the meter,
and shall
open and backfill a service trench 36” minimum
depth from the L.E.C. equipment to the desired meterbase
location.
- The Cooperative shall furnish and maintain the meter and electrical
cable from the transformer to the meter.
- Before the cooperative
energizes the meterbase, the base must be inspected and
approved by the State or City Electrical
Inspectors and the cooperative personnel. The service trench must
be completely backfilled.
- Before you dig, call 48 hours in advance
to the Utility Notification Center 1-800-332-2344.
Underground Service To A Building

Notes:
- All electrical connections, equipment and equipment grounds
shall comply with the National Electrical Code.
- The consumer
shall furnish and maintain all conduit, conduit straps,
grounds, meterbase, disconnects, and electrical cable
beyond the meter, and shall open and backfill a service
trench 36” minimum depth from the LEC equipment to
the desired meterbase location.
- The Cooperative shall furnish and maintain
the meter, electrical cable from LEC equipment to the meter.
- Before
the cooperative energizes the meterbase, the base must
be inspected and approved by the State or City Electrical
Inspectors and the cooperative personnel. The service trench must
be completely backfilled after approved inspection.
- Before you
dig, call 48 hours in advance to the Utility Notification
Center 1-800-332-2344.
|